Angus completes annual shutdown at Saltfleetby
Angus Energy
0.30p
16:55 20/12/24
Angus Energy announced on Wednesday that it has successfully completed its planned annual maintenance shutdown at the Saltfleetby site, finishing on 13 July.
FTSE AIM All-Share
710.60
17:04 20/12/24
The AIM-traded firm said the maintenance and improvement projects, including the installation of compressor acoustic hoods, were executed within the scheduled five-day outage.
It noted that the shutdown was accomplished without any safety incidents or environmental harm.
Following the maintenance, dual compressor operations resumed in the afternoon of 13 July.
The first day saw a sales gas export rate of 6.75 million standard cubic feet per day (mmscfd).
At 1404 BST, shares in Angus Energy were down 7.69% at 0.3p.