Vedanta Resources said it had maintained aluminium production guidance at 1.2m tonnes a year despite a power shut down at one of its plants in August.
FTSE 250
20,831.84
16:39 20/09/24
n/a
n/a
FTSE 350
4,543.89
16:49 20/09/24
n/a
n/a
FTSE All-Share
4,501.08
17:04 20/09/24
n/a
n/a
Mining
11,503.14
16:49 20/09/24
0.18%
20.17
Vedanta Resources
832.60p
16:35 28/09/18
0.87%
7.20p
The commissioning of pots at the first line of the company's Jharsuguda-II aluminium smelter was completed in end-July 2016, it added.