Vedanta maintains FY aluminium production guidance at 1.2m tonnes
Vedanta Resources said it had maintained aluminium production guidance at 1.2m tonnes a year despite a power shut down at one of its plants in August.
FTSE 250
20,522.81
16:38 14/11/24
n/a
n/a
FTSE 350
4,459.02
16:38 14/11/24
n/a
n/a
FTSE All-Share
4,417.25
16:54 14/11/24
n/a
n/a
Mining
10,475.37
16:38 14/11/24
-1.86%
-198.96
Vedanta Resources
832.60p
16:35 28/09/18
0.87%
7.20p
The commissioning of pots at the first line of the company's Jharsuguda-II aluminium smelter was completed in end-July 2016, it added.
"The first line was impacted by a pot failure incident due to a power shut down in early August, post which 168 pots were taken out of production. The impacted pots are currently being repaired and relined," the firm said.